On the Utah

Part of On the record
Business

Salt Lake City Bans New Data Centers for Six Months

·

Add On the record as a preferred source on Google
Salt Lake City
File photo: Salt Lake City. Photo: Ricardo630 (CC BY-SA 3.0) via Wikimedia Commons

Key facts

  • The Salt Lake City Council approved a six-month moratorium on new data centers in manufacturing and business park districts1
  • The ban runs for 180 days, the maximum allowed under state law1
  • The city will use the time to draft new rules on energy and water use, noise, heat, lighting and air quality1 2
  • A proposed data center near Northpoint homes is already under review and could still move forward under existing zoning2

The Salt Lake City Council voted Tuesday to temporarily prohibit new data center development while the city works on new rules for the facilities..2 The 6-0 vote came with one member absent, after the council altered its agenda at the eleventh hour Monday to add the item, which passed without a public hearing.1

The ordinance removes data centers as an allowed use in manufacturing and business park districts for 180 days, the maximum period for such a ban allowed under state law..1 City officials are directed to use the six-month interim to draft new development and zoning rules to address the impacts from data center projects on energy and water usage, as well as propose mitigation measures for impacts from noise, heat, lighting and any other issues identified.1

A pause for water and power

Mayor Erin Mendenhall earlier Tuesday called the step “a healthy pause.”.1 The mayor said the city’s land-use rules “never contemplated these massive data centers” and that issues around their water usage alone are “tremendously in flux as that industry is evolving rapidly.”.1 The city, which faces longstanding drought conditions, recently passed a permanent 200,000-gallon daily cap on water consumption for non-residential land uses.1

The ordinance says the ban is needed to protect the city’s water resources, prevent residents' electricity bills from rising and ensure that data center projects are subject to public input.1

Northpoint project under review

Many first learned last week of Florida development company Qlevr LLC’s applications for a state air-quality permit and city building clearance in pursuit of constructing a one-story, $105 million data center at 2258 W. 2950 North..1 The proposed center would be powered by the standard electrical grid and located on an open lot directly south of and across 2200 West from multiple homes, not far from the fragile fringe of the Great Salt Lake.1

Council staff told FOX 13 News the temporary prohibition would delay the city’s review of the Northpoint application, and that an existing development agreement gives the property rights under its current zoning..2 That means any new city regulations would not apply to the project unless the developer voluntarily agreed to follow them..2 Qlevr has also proposed data centers in Indiana and Minnesota.2

Council members weigh in

District 1 council member Victoria Petro, who represents Northpoint, said the city has been working on the issue for some time..1 2

Who reported it

Report an error in this story

Sources

The numbers in the story point here. Each one links to the original article.

    See a sentence its source doesn’t back up?

    Tell us the source number and what’s wrong. We check every report. If we change the story, the fix goes on the corrections page with the old wording.